Cost blowouts, project delays as ‘hidden’ stormwater drain extends commuter pain (opens original article in a new tab)

TL;DR

Queanbeyan's Monaro Street closure has been extended due to the unexpected discovery of a century-old stormwater drain, causing delays and increased costs for a major CBD upgrade project.

  • Monaro Street closure extended due to a century-old stormwater drain discovery.
  • Project costs have increased by 28% and timeline has been delayed beyond September 2026.
  • Council seeks $3.25 million in funding to address the stormwater main issue.